Pre-bid Meeting Conversation


Pre-bid meeting Start Time ( 15/07/2021 14:30 )
Pre-bid meeting End Time ( 15/07/2021 15:30 )

Sr.no. User Comment
1 Anup G / Manager (C) -OPS ( 15/07/2021 02:30 ) Welcome to Pre-bid meeting.
2 Anup G / Manager (C) -OPS ( 15/07/2021 02:30 ) You may raise your questions now.
3 1. ELECTRONICS CORPORATION OF INDIA LTD ( 15/07/2021 02:36 ) Thank you sir We have sent our pre-bid queries vide our email dated-13.07.2021. Confirm its receipt.
4 Anup G / Manager (C) -OPS ( 15/07/2021 02:38 ) Yes
5 2. ELECTRONICS CORPORATION OF INDIA LTD ( 15/07/2021 02:38 ) kindly arrange clarifications to our queries sent
6 Anup G / Manager (C) -OPS ( 15/07/2021 02:39 ) Response to queries, shall be uploaded as pre-bid MOM.
7 Anup G / Manager (C) -OPS ( 15/07/2021 02:59 ) Pre-bid meeting will end in thirty minutes. Any queries may please be asked before the closure of the pre-bid meeting time.
8 3. ELECTRONICS CORPORATION OF INDIA LTD ( 15/07/2021 03:03 ) Specification of Biscuit PC (700MWE_60000_2082_ISS_R0): Specification calls for mounting PC suitable to 1U Space in 19"Rack. Biscuit PC as per specifications does not available in 1U height . Kindly clarify / suggest alternative.
9 Anup G / Manager (C) -OPS ( 15/07/2021 03:04 ) Your query is being examined and response shall be uploaded as pre-bid MOM.
10 Anup G / Manager (C) -OPS ( 15/07/2021 03:04 ) Bidders need not repeat the queries already submitted by email as these shall be addressed along with response to all the queries.
11 4. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:10 ) Sir, We need to visit the site to understand I&C requirements. request to confirm whether we can visit one site for study.
12 5. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:14 ) whether all systems for nine sites to be qualified.
13 6. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:15 ) Please elaborate software requirements, scope of work and development environment.
14 7. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:18 ) Request you to provide detailed BOM for all items with Manufacturer part nos. (This is required for cost estimation)
15 Anup G / Manager (C) -OPS ( 15/07/2021 03:19 ) All unanswered queries will be responded along with the consolidated response to all the queries raised by all the bidders.
16 8. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:20 ) we would like to know if local NPCIL QA will coordinate or QA will be from respective sites.
17 9. ELECTRONICS CORPORATION OF INDIA LTD ( 15/07/2021 03:23 ) Is there any price adjustment clause applicable to Installation and commissioning?
18 10. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:24 ) In case of Obsolescence of components, If alternate components calls for PCB changes. we assume that NPCIL will update the GERBERS.
19 11. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:26 ) We request NPCIL to provide Software loading tools for all PCB Boards(eg. PRAN Board, etc).
20 12. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:26 ) Please Elaborate IV&V Scope of work
21 13. SLN Technologies Pvt. Ltd. ( 15/07/2021 03:28 ) Please spicify the distance between two racks and specify how the field signal are terminated. How long should the cables be?
22 14. ELECTRONICS CORPORATION OF INDIA LTD ( 15/07/2021 03:28 ) Liquidated damages shall be recovered for undelivered portion and not on total contract value
23 Anup G / Manager (C) -OPS ( 15/07/2021 03:29 ) Response to all the queries shall be uploaded as pre-bid MOM
24 Anup G / Manager (C) -OPS ( 15/07/2021 03:29 ) Thank you for participating in the pre-bid meeting.